The NCC is Australia’s primary set of technical design and construction requirements for buildings and plumbing systems. It sets the minimum standards for safety, health, amenity, accessibility and sustainability.

The NCC is developed by the Australian Building Codes Board and adopted and administered by each state and territory through their own legislation

The National Construction Code (NCC) 2025 commenced in Tasmania on 1 May 2026. However, recent legislative changes mean this arrangement was temporary.

The Building Amendment Bill 2026 has now passed both Houses of Parliament with amendments. From 5 June, NCC 2022 again applies in Tasmania until 1 May 2027, after which time NCC 2025 will be adopted.

Effect of the Building Amendment Act 2026

The Building Amendment Bill 2026 has now passed both Houses of Parliament with amendments.

The Building Amendment Act 2026 took effect on 5 June 2026, this means:

  • NCC 2025 will no longer apply in Tasmania (subject to any transitional arrangements);
  • NCC 2022 will be reinstated as the applicable Code; and

NCC 2022 will remain in effect until 1 May 2027.

Transitional arrangements and exemptions

The Building Act 2016 contains transitional provisions that may provide exemptions from application of the current NCC in certain circumstances.

Under section 11(5) of the Act, exemptions may apply where:

  • a certificate of likely compliance for the work was issued before the Code was adopted in Tasmania; or
  • a building surveyor or relevant permit authority certifies in writing that substantial progress had been made on the design of the work before adoption of the provision by the State; or
  • substantial progress had occurred before a relevant referenced standard was amended.

Further information

Last updated: 05 Jun 2026

This page has been produced and published by the Consumer Building and Occupational Services Division of the Department of Justice. Although every care has been taken in production, no responsibility is accepted for the accuracy, completeness, or relevance to the user's purpose of the information. Those using it for whatever purpose are advised to verify it with the relevant government department, local government body or other source and to obtain any appropriate professional advice. The Crown, its officers, employees and agents do not accept liability however arising, including liability for negligence, for any loss resulting from the use of or reliance upon the information and/or reliance on its availability at any time.